The Village Trunk Water Main - Stage 2



 

Job No:

357

Client:

Economic Development Queensland

Project Location:

Residential Estate, Oonoonba, Townsville

Approximate Value:

$417,000

Contract Time:

14 Weeks

Completion Date:

December 2014

Engineer:

UDP Consulting Engineers

Referee:

UDP Consulting Engineers, Paul Petersen, (07) 4772 0666

 

The Village Trunk Water Main Stage 2 involved the supply and construction of DN375 PVC water main and its fittings over a length of 493m; including connection to an existing DN225 DICL water main in Queens Road. It also involved directional drilling under Queens Road for the 28m long x 800mm diameter steel pipe enveloper of the DN450 DICL water main.  

A pdf copy of this project can be downloaded here. (Download PDF)

 

Go to top of page