Corbett Street DN300 Trunk Sewer Extension



 

Job No:

347

Client:

Townsville City Council

Project Location:

Corbett Street, Townsville

Approximate Value:

$710,000

Contract Time:

12 Weeks

Completion Date:

March 2014

Engineer:

UDP Consulting Engineers

Referee:

AECOM Australia Pty Ltd, Glenn Stephens, (07) 4728 3214

 

The Corbett Street DN300 Trunk Sewer Extension involved the supply and construction of 418m x DN300 PVC gravity sewer and 40m x DN300 DICL gravity sewer, from the existing DN300 sewer on the southern side of Ingham Road through to the existing DN300 sewer on the southern side of Woolcock Street; including micro-tunnelling under Woolcock Street and the North Coast Railway Line in accordance with QR and DTMR requirements.  Associated works included the supply & construction of 7 concrete maintenance holes (6 x DN1050 & 1 x DN1200) and the connection into 2 existing maintenance holes (DN1050).

A pdf copy of this project can be downloaded here. (Download PDF)

 

Go to top of page

Home | About Us | Projects | Clients | Contact Us

All contents Copyright 2014 NQ Excavations Pty Ltd.
All rights reserved. Disclaimer. 2014.